October 2019

At the beginning of October, the building's central boiler with accumulator was put into operation and the completion of the common areas is now in full swing. Some clients have also completed their apartments and the residence is filling up with new tenants.

October 2019
October 2019
October 2019
October 2019

April 2019

During the third week of April, the apartment interiors will be completed to a white walls finish.

April 2019
April 2019
April 2019

March 2019

The machine-applied base coat plastering on the walls of the 4th and 5th floors of the residence is now complete. This week, the concrete floors will be poured.

March 2019
March 2019
March 2019
March 2019

January 2019

The apartment owners association was founded based on a statement by the owner, whose deposit was made on December 5th, 2018, with legal effects as of November 6th, 2018. By the end of January 2019, we will ensure its creation by registering it in the public register.

January 2019

December 2018

Mr. Černý from the Ústecký region is manufacturing new entry doors for your apartment in his family's workshop.